Prefab & Shape Laser (depending on process) 2 Weeks
Turning (Depending on the part.) 2 Weeks
VBM (Depending on the part.) 3 Weeks
Milling (Depending on the part.) 2 Weeks
Surface Grinding 2 Weeks
Machining 3 Weeks
Horizontal Bar 3-4 Weeks
Welding 3 Weeks
Stress Relieving Add 2 Days
Shot Blast 2 Weeks
Paint 1 Week
O.S. Operations (Plating, H.T., Galv., etc.) Add 1-2 Weeks
First Article Reports Add 1-5 Days